Pinnacle Peak public record

Comments due Nov. 30, 5 p.m.

Pinnacle Peak timeline

In brief

The City Council approved the R-3 rezone of the 38 first-phase acres on Oct. 14, 2025, and adopted Ordinance 2025-06 on Dec. 9, 2025 (council minutes, Oct. 14, 2025, pp. 5-6; council minutes, Dec. 9, 2025, p. 2). On Oct. 9, 2026, the city stamped received the revised preliminary plat application, the annexation application and the comprehensive plan amendment (preliminary plat application, p. 1; annexation application, p. 1; comprehensive plan amendment application, p. 1). The Planning and Zoning Commission's hearing on the plat is Dec. 7, 2026, at 7 p.m., and written comments are due by 5 p.m. Nov. 30 (hearing notice, p. 1). Dates set in the records run into 2027, and the Water Supply Bank leases on four of the water rights end Dec. 31, 2028 (IDWR letter, Nov. 14, 2025, p. 4; IDWR letter, July 9, 2025, p. 25).

The hearing is Dec. 7; dates set in the records run to the end of 2028

The council approved the rezone on Oct. 14, 2025; the city received the plat, annexation and plan filings on Oct. 9, 2026; the Water Supply Bank leases end Dec. 31, 2028.

Key dates, 2025 to 2028Oct. 14, 2025: Council approves the rezone, 3-1; Dec. 9, 2025: Ordinance 2025-06 adopted; Sept. 30, 2026: Water Ordinance 2026-09 adopted; Oct. 9, 2026: Plat, annexation, plan filings received; Nov. 30, 2026, 5 p.m.: Written comments due; Dec. 7, 2026, 7 p.m.: Commission hearing on the plat; Jan. 21, 2027: Staff timeline: recommendation; April 14, 2027: Condition date in notice of decision; May 14, 2027: Condition date in Ordinance 2025-06; Dec. 31, 2028: Water Supply Bank leases end. Drawn to a time scale: solid dots are actions taken, heavy rings the comment deadline and hearing, gray rings dates set in the records.2026202720282025Oct. 14, 2025: Council approves the rezone, 3-1Dec. 9, 2025: Ordinance 2025-06 adoptedACTIONS TAKENOct. 14, 2025Council approves the rezone, 3-1Dec. 9, 2025Ordinance 2025-06 adoptedSept. 30, 2026: Water Ordinance 2026-09 adoptedOct. 9, 2026: Plat, annexation, plan filings receivedNov. 30, 2026, 5 p.m.: Written comments dueDec. 7, 2026, 7 p.m.: Commission hearing on the platSept. 30, 2026Water Ordinance 2026-09 adoptedOct. 9, 2026Plat, annexation, plan filings receivedCOMMENT DEADLINE AND HEARINGNov. 30, 2026, 5 p.m.Written comments dueDec. 7, 2026, 7 p.m.Commission hearing on the platJan. 21, 2027: Staff timeline: recommendationDATES SET IN THE RECORDSJan. 21, 2027Staff timeline: recommendationApril 14, 2027: Condition date in notice of decisionMay 14, 2027: Condition date in Ordinance 2025-06April 14, 2027Condition date in notice of decisionMay 14, 2027Condition date in Ordinance 2025-06Dec. 31, 2028: Water Supply Bank leases endDec. 31, 2028Water Supply Bank leases end

Sources: the entries for these dates in the sections below. Drawn to a time scale; a bracket ties each group of labels to its dates on the line.

Show the figures as a table
DateEvent
Oct. 14, 2025Council approves the rezone, 3-1
Dec. 9, 2025Ordinance 2025-06 adopted
Sept. 30, 2026Water Ordinance 2026-09 adopted
Oct. 9, 2026Plat, annexation, plan filings received
Nov. 30, 2026, 5 p.m.Written comments due
Dec. 7, 2026, 7 p.m.Commission hearing on the plat
Jan. 21, 2027Staff timeline: recommendation
April 14, 2027Condition date in notice of decision
May 14, 2027Condition date in Ordinance 2025-06
Dec. 31, 2028Water Supply Bank leases end

The record, section by section

About this timeline

This timeline lists, by year, the land sales, water rights changes and city reviews behind the Pinnacle Peak proposal. Each entry links to the record it comes from, cited to the page. News reports appear only where no record covers an event and are labeled as news.

Dates in 2027 and 2028 are deadlines and timelines stated in the records.

2022: the first buyer registers

DateWhat happenedSource
June 7 862 Teton, LLC registers with the Texas Secretary of State. In 2025 it bought land and water rights in Section 29 and conveyed parts of them to PFG Idaho LLC, Teton Commercial Holdings LLC and Teton Valley Water, LLC. Texas Comptroller record, 862 Teton, LLC, checked Nov. 18, 2026; deed 290683, p. 1; IDWR notice, 862 Teton, p. 1; deed 290685, p. 2; deed 290686, p. 1; quitclaim deed 292111, p. 2

2024: Water Supply Bank leases

DateWhat happenedSource
Jan. 1 Water rights 22-2128 and 22-10835 (Lease 1807) and 22-2281 (Lease 1806) begin Water Supply Bank leases that run through Dec. 31, 2028. The rights later passed to 862 Teton, which conveyed split portions to PFG Idaho and the rest to Teton Valley Water. IDWR water right reports, Nov. 13, 2025, pp. 6, 8-13; IDWR letter to PFG Idaho, July 9, 2025, p. 25

2025: land, water rights and the rezone

DateWhat happenedSource
May 21 PFG Idaho LLC files with the Idaho Secretary of State, which lists it as formed in Idaho. Idaho Secretary of State record, checked Nov. 18, 2026, p. 1
May 22 McCulloch Ranches LLC executes a warranty deed dated May 22 conveying land in Section 29, Township 6 North, Range 45 East, to 862 Teton LLC (acknowledged June 18; recorded as Instrument 290683). Deed 290683, pp. 1, 3
May 23 Teton Commercial Holdings LLC files with the Idaho Secretary of State. Idaho Secretary of State record, checked Nov. 18, 2026, p. 1
June 6 862 Teton executes two warranty deeds dated June 6 (acknowledged June 19 and June 20). Deed 290685 conveys land in Section 29 to PFG Idaho LLC with portions of water rights 22-2128 and 22-10835, "a combined total of 25.8 acres and 0.30 cfs," and of 22-2281, "64.7 acres with 0.70 cfs." Deed 290686 conveys land to Teton Commercial Holdings LLC and states, "All water rights are reserved by the Grantor." Deed 290685 calls PFG Idaho "a Texas limited liability company"; the Idaho Secretary of State lists it as formed in Idaho. Deed 290685, pp. 1-2, 4; deed 290686, pp. 1-2; Idaho Secretary of State record, p. 1
June 16 McCulloch Ranches executes a second warranty deed to 862 Teton, dated June 16 (acknowledged June 18; recorded as Instrument 290684). Deed 290684 in IDWR ownership file, pp. 2, 6
June 20 The Teton County Recorder records deeds 290683, 290684, 290685 and 290686, each at 1:33 p.m. Deed 290683, p. 1; deed 290684, p. 2; deed 290685, p. 1; deed 290686, p. 1
June 25 The Idaho Department of Water Resources (IDWR) receives two ownership notices: McCulloch Ranches to 862 Teton for five water rights, and 862 Teton to PFG Idaho for split portions of 22-2128, 22-10835 and 22-2281. Both give June 13, 2025, as the date acquired. IDWR notice, 862 Teton, p. 1; IDWR notice, PFG Idaho, p. 1
July 3 IDWR acknowledges 862 Teton LLC as owner of water rights 22-2128, 22-2281, 22-10831, 22-10832 and 22-10835. Its letter notes that 22-2128, 22-2281 and 22-10835 "were leased to the Water Supply Bank" in 2024 and stay in the bank until Dec. 31, 2028, "unless released earlier." IDWR letter, July 3, 2025, p. 20
July 9 IDWR splits the three rights, creating 22-14668, 22-14669 and 22-14670 for PFG Idaho LLC. Its letter to PFG Idaho says 22-14670 "is also leased to the Bank" until Dec. 31, 2028, unless released earlier. IDWR letter, July 9, 2025, p. 25; IDWR split report, p. 2
July 15 PFG Idaho LLC signs its application to the City of Tetonia to rezone the land. City rezone application, PFG Idaho, July 15, 2025, p. 2
Aug. 8 Teton Valley Water, LLC registers with the Texas Secretary of State. Texas Comptroller record, Teton Valley Water, LLC, checked Nov. 18, 2026
Aug. 21 Date of the applicant's narrative for the rezone and conditional use permit, as listed in the city staff memo's attachments. Staff memo, Sept. 3, 2025, p. 4
Sept. 2 Sunrise Engineering, for the city, reviews the concept plan: "There are approximately 100 connections of capacity in the existing sewer and water system," to be verified by facilities planning updates. The letter notes that "The developer has proposed to transfer water rights to the City." Sunrise Engineering letter, Sept. 2, 2025, pp. 1-2
Sept. 3 The city's contract planner issues a staff memo to the Planning and Zoning Commission on a rezone of 38 acres from Transitional Agriculture to R-3, high density residential, and a conditional use permit "for allowance to pursue platting up to 90 single-family homes." It lists PFG Idaho, LLC as owner. Staff memo, Sept. 3, 2025, p. 1
Sept. 8 The Planning and Zoning Commission holds a public hearing; the minutes record "No public comment." The commission recommends the rezone (Wood moved, Fox seconded) and the conditional use permit (Wood moved, Weltman seconded), each conditioned on a subdivision application "within 1 calendar year." The minutes say each motion passed and give no tally. P&Z minutes, Sept. 8, 2025, pp. 2-3
Sept. 8 862 Teton signs a quitclaim deed giving Teton Valley Water, LLC "all of Grantor's right title and interest" in water rights 22-2128, 22-2281 and 22-10835, acknowledged before a notary in Dallas County, Texas. Quitclaim deed 292111, p. 2
Sept. 19 The Teton County Recorder records the quitclaim deed as Instrument 292111. Quitclaim deed 292111, p. 2
Oct. 7 Written comments are due for the City Council hearing on the rezone and conditional use permit. Council hearing notice, p. 1
Oct. 14 The City Council holds a public hearing and approves the rezone to R-3, 3-1 (Ball moved, Hansen seconded, Rasmussen voting no), on condition that a subdivision application be "submitted within 18 months from the date of this motion." It approves the conditional use permit for single-family homes, 3-1 (Hansen moved, Bonilla seconded, Rasmussen voting no). City Council minutes, Oct. 14, 2025, pp. 5-6
Oct. 29 IDWR receives Teton Valley Water's notice of change in ownership for 22-2128, 22-10835 and 22-2281. IDWR notice, Teton Valley Water, p. 1
Nov. 12 The City Council tables Rezone Ordinance 2025-06 "so that a full voting quorum can be present." Councilman Hansen abstains, and Councilman Ball is absent. City Council minutes, Nov. 12, 2025, p. 2
Nov. 14 IDWR acknowledges Teton Valley Water LLC as owner of 22-2128, 22-2281 and 22-10835, which it says remain in the Water Supply Bank until Dec. 31, 2028, unless released earlier. IDWR letter, Nov. 14, 2025, p. 4
Dec. 9 The City Council adopts Ordinance 2025-06, the Pinnacle Peak rezone, by roll call (Bonilla, Rasmussen and Ball yes; Hansen absent), after the city attorney says required notice and publication were completed. City Council minutes, Dec. 9, 2025, p. 2; council minutes, Aug. 11, 2026, p. 4
Dec. 9 The city's notice of decision (ZX2025-1) takes effect. It requires a subdivision application "within 18 months from the date of this approval (4/14/2027)" and states that "If the subdivision is not applied for, denied, or the application and/or approval expires, the zone shall revert back to Transitional Agriculture (TA)." The council's Oct. 14 motion lists reversion if the subdivision "is not applied for" or its review or approvals "expire," and does not name denial. Notice of decision, pp. 1, 4; council minutes, Oct. 14, 2025, pp. 5-6
Dec. 11 and 13 Traffic counts for the applicant's three KLOA studies are taken on a Thursday, Dec. 11, and a Saturday, Dec. 13. The studies increase the counts by 52 percent "to reflect the peak season." KLOA Phase I study, pp. 8-9; KLOA baseball resort study, pp. 8-9; KLOA master plan study, pp. 13-14
Dec. 16 The city receives the Pinnacle Peak subdivision concept plan. Staff report, Oct. 28, 2026, p. 2
Dec. 23 TischlerBise submits its impact analysis report on the development to Powell Family Group. TischlerBise report, p. 1
Dec. 24 A request for reconsideration of the rezone and conditional use permit is made, according to the city attorney, by "a Valley Advocates for Responsible Development (VARD) chosen attorney." City Council minutes, Jan. 13, 2026, p. 2

2026: applications, reviews and the hearing

DateWhat happenedSource
Jan. 13 The City Council votes not to entertain the reconsideration request, 3 ayes and one abstention (Ball moved, Rasmussen seconded), after the city attorney says it was untimely because the notice of decision was published Dec. 9 and the request came after the 14-day period allowed. Councilman Hansen "recuses himself from this topic due to a conflict of interest." Concept review then proceeds. City Council minutes, Jan. 13, 2026, pp. 2-3; staff report, p. 2
Jan. 16 The applicant's draft annexation agreement refers to an annexation application "dated as of or about January 16, 2026." Draft annexation agreement, Recital N
Jan. 20 The city clerk asks service providers to comment on a concept subdivision of 150 units, "up to 90 single family homes and 60 townhouses." Clerk's email, Jan. 20, 2026, in the applicant's annotated copy of the city's concept review file, pp. 13-14
Feb. 3 Sunrise Engineering sends the city its review of the concept plan. Sunrise Engineering letter, Feb. 3, 2026, in the applicant's annotated copy of the city's concept review file, p. 16
Feb. 9 David Ferrette, the developer, signs a comprehensive plan amendment application. The contract planner records that "On 2/9/26 a Comp Plan Amendment application was received along with an Annexation Application of the surrounding area." Comprehensive plan amendment application, p. 1; planner's concept memo, Feb. 16, 2026, applicant's annotated copy, p. 7
Feb. 13 Date of the applicant's geotechnical soil study by Allied Consulting Services, as cited in the applicant's drainage report. Eagle Rock drainage report, p. 12
Feb. 16 The city's contract planner sends the applicant written comments on the concept subdivision. Contract planner memo, Feb. 16, 2026, applicant's annotated copy, p. 1; staff report, p. 2
March 2 The Planning and Zoning Commission reviews the concept plan in a work session. Staff later writes that comments from the commission and service providers "concluded that the Concept Subdivision, as designed, did not conform," citing the block layout, open space and road connections. Staff report, Oct. 28, 2026, p. 2
May 20 The city's contract planner asks service providers to comment on the Pinnacle Peak Business Park rezone, 4.66 acres from R-1 to C-2 for mixed-use buildings with 48 residential units. ITD and city email thread, May 20 to Aug. 24, 2026, p. 8
May 21 Date of KLOA’s traffic impact study for Pinnacle Peak Phase I, prepared for Powell Family Group. KLOA Phase I study, May 21, 2026, p. 1
May 28 The Idaho Transportation Department's district traffic engineer replies that there is "not enough turn lane approach" and that "Developers need to conduct a Traffic Impact Study." ITD and city email thread, pp. 5-6
June 16 The city posts notice of a July 6 Planning and Zoning Commission hearing on rezoning 4.66 acres from R-1 to C-2 for "up to 5 separate live/work buildings containing approximately 46 residential units and 51,620SF of commercial space." David Ferrette is the applicant for owner PFG Idaho, LLC, "as part of the Pinnacle Peak Development." P&Z hearing notice, posted June 16, 2026, p. 1
June 29 ITD writes that it will require the developer to make roadway improvements at both proposed highway accesses "beginning in the first phase of development." ITD and city email thread, p. 3
July 1 Written comments are due for the July 6 business park rezone hearing. P&Z hearing notice, p. 1
July 6 The city's notice sets the Planning and Zoning Commission's hearing on the 4.66-acre business park rezone request for this date. P&Z hearing notice, p. 1
July 14 Date of the applicant's Eagle Rock Engineering sewer and water reports. The sewer report's page footer reads July 9. The sewer report lists "57,130 gpd (386 ERU's)" as remaining capacity; the reports of Nov. 18 replace both, and the new sewer report lists 88 ERUs available before upgrades. Eagle Rock sewer report, pp. 1, 3; Eagle Rock water report, p. 1; Nov. 18 sewer report, p. 3
July 15 Date of the applicant's Eagle Rock preliminary plat sheets. The city stamps KLOA's May 21 Phase I traffic study "RECEIVED 7-15-2026." Eagle Rock drainage report, p. 15; KLOA Phase I study, p. 1
July 20 Teton County Properties, LLC signs an IDWR application, later numbered Transfer 90613, to move part of water rights 22-2128 and 22-10835. Transfer 90613 application, pp. 4, 8
July 21 The city deems the first preliminary plat application complete and sends it to service providers. Staff report, p. 2
July 22 IDWR receives Transfer 90613. The application states, "Applicant proposes to transfer a portion of water rights that are under contract for purchase," and would move 22 irrigated acres' worth of the rights from Section 29, Township 6 North, to land in Sections 21 and 22, Township 4 North, Range 45 East, for irrigation and wildlife storage. Transfer 90613 application, pp. 1, 3; legal notice, p. 42
Aug. 3 Mayor Brent Schindler writes to the Idaho Department of Parks and Recreation (IDPR) about the Ashton Tetonia Trail and a request for perpetual easements across it for the development, according to IDPR's reply. IDPR letter, Oct. 9, 2026, p. 1
Aug. 6 Date of the applicant's Eagle Rock preliminary drainage report. Eagle Rock drainage report, p. 1
Aug. 10 The applicant submits a revised master plan, and the city sends service providers a revised request for comment. Staff report, p. 2
Aug. 11 The City Council adopts Ordinance 2026-06, which corrects the parcel number in Ordinance 2025-06, a "clerical error" according to the minutes, 3 ayes with Councilman Hansen abstaining (Hill moved, Rasmussen seconded). City Council minutes, Aug. 11, 2026, p. 4
Aug. 19 Date of KLOA's traffic impact study for the National Parks Baseball Resort, prepared for the resort. KLOA baseball resort study, p. 1
Aug. 20 Sunrise Engineering, for the city, reviews the first preliminary plat, which "consists of three phases." Sunrise Engineering letter, Aug. 20, 2026, p. 1
Aug. 24 ITD tells the city it will allow one highway access at Asher or Chloe Circle and one at Lucas Lane, will require the developer to give right of way for future expansion, and that "Signals are required at Lucas Lane, Chloe/Asher, and Perry Ave given the traffic impacts to the highway, warranted from this development." ITD email, Aug. 24, 2026, p. 1
Sept. 1 Teton School District #401 asks that the subdivision "voluntarily contribute $164,340" to its School Growth Contribution Fund. The city stamps the letter received Sept. 10. School district letter, Sept. 1, 2026, p. 1
Sept. 8 The City Council approves the city's wastewater facility planning study (Hill moved, Ball seconded, unanimous). The city engineer suggests changing the city's drinking water code "to require new developments to contribute water rights"; no motion is made. City Council minutes, Sept. 8, 2026, p. 3
Sept. 11 Date of KLOA's traffic impact study for Pinnacle Peak Phase I, prepared for Powell Family Group. KLOA Phase I study, p. 1
Sept. 15 The contract planner's memo for a Planning and Zoning Commission work session set for this date covers the expanded Pinnacle Peak concept, which now includes a baseball resort. It states, "Because no formal application has been submitted, this session is purely informational." Contract planner memo, Sept. 15, 2026, p. 1
Sept. 16 IDWR acknowledges Transfer 90613, schedules its legal notice for Sept. 23 and 30, and asks the Water District 122 watermaster for a recommendation within 21 days. IDWR letter, Sept. 16, 2026, p. 40; IDWR email to watermaster, p. 1
Sept. 17 PFG Idaho signs its annexation application for 389.25 acres. Annexation application, pp. 1-2
Sept. 23 and 30 The Transfer 90613 notice runs in the Teton Valley News. Affidavit of publication, p. 1
Sept. 30 The City Council adopts Ordinance 2026-09, "Drinking Water Capacity and Water Rights Requirements for Future Development," after a public hearing with no public comment (Ball moved, Rasmussen seconded; Hill, Rasmussen and Ball yes; Hansen absent). It also approves the drinking water facility planning study (Rasmussen moved, Hill seconded). City Council minutes, Sept. 30, 2026, pp. 1-2
Oct. 9 The city stamps received the revised preliminary plat application, the annexation application (AX2026-3), the comprehensive plan amendment (AMD2026-1), narratives and the applicant's engineering and traffic studies, including KLOA's master plan transportation study dated the same day. Preliminary plat application, pp. 1, 3; annexation narrative, p. 1; comprehensive plan amendment narrative, p. 1; alternative design plan, p. 1; KLOA master plan study, p. 1
Oct. 9 IDPR "respectfully rejects the proposal for a one-time payment of $6,600.00 for three easements" across the Ashton Tetonia Trail and asks for the developer's traffic study. IDPR letter, Oct. 9, 2026, p. 1
Oct. 13 The city deems the revised preliminary plat application complete, after a redesign that removed a highway access and changed the open space and townhouse layout. The updated master plan is stamped received. Staff report, p. 2; master plan, p. 1
Oct. 13 Deadline for protests to Transfer 90613. Legal notice, p. 42
Oct. 15 The city sends the revised plat to service providers for comment. Staff report, p. 3; Teton Valley Housing letter, p. 1
Oct. 22 and 26 Teton County Fire District (Oct. 22) and RAD Curbside (Oct. 26) send comments. Staff report, p. 3
Oct. 27 City staff and service providers meet with the developer team. Staff report, p. 2
Oct. 28 The contract planner issues a staff report for the Nov. 2 meeting, stating that "Neither Staff nor Service Providers have had sufficient time to fully review and offer any recommendations at this time." Staff report, Oct. 28, 2026, p. 1
Oct. 30 Teton Valley Housing comments on the plat's workforce housing component. Teton Valley Housing letter, Oct. 30, 2026, p. 1
Nov. 2 The Planning and Zoning Commission holds an initial review of the revised plat, where "P&Z is not being asked to make a recommendation." The service providers' 20-day review period ends. The planner later records that the commission supported asking for an updated rendering of the townhouses and open space. The Valley Signal reported that the commission took no action and asked for more time, an attorney and a planning director (news report). Staff report, pp. 1-2; planner memo, Nov. 16, 2026, p. 2; The Valley Signal, Nov. 5, 2026 (news)
Nov. 11 The school district revises its letter, repeating the $164,340 request and adding that "An appropriate size for the forecasted growth of Tetonia would be five acres" for a future school site. School district letter, Nov. 11, 2026, pp. 1-2
Nov. 12 Sunrise Engineering, for the city, reviews the revised plat and recommends that the city "request revised reports and plans before final action on the Preliminary Plat." Sunrise Engineering letter, Nov. 12, 2026, p. 1
Nov. 16 The agenda for a joint special meeting and work session of the City Council and the Planning and Zoning Commission lists one item, "Comprehensive Plan Draft Review." The same day, the contract planner sends the city clerk a review memo on the plat. Joint session agenda, Nov. 16, 2026; planner memo, Nov. 16, 2026, p. 1
Nov. 18 The city posts notice of the Dec. 7 hearing. The same day, IDWR's document list for 22-2128 shows the Transfer 90613 application and the affidavit of publication, with no approval or denial filed. Eagle Rock Engineering dates new water and sewer reports for the applicant: 0 water ERUs and 88 sewer ERUs available before upgrades, and "Phase 3 will exceed the 88 available ERU's." Hearing notice, posted Nov. 18, 2026, p. 1; IDWR document list, 22-2128, checked Nov. 18, 2026; Eagle Rock water report, Nov. 18, 2026, p. 3; sewer report, pp. 3-4
Nov. 19 The city receives the applicant's resubmittal: a revised preliminary plat, revised renderings, the Nov. 18 water and sewer reports and a worksheet answering the fire district's and city engineer's comments. The plat now dedicates two open-space lots to the city, down from four, and the roundabout is removed. The draft development agreement is not revised. Response worksheet, received Nov. 19, 2026, pp. 1, 7, 12; revised plat, sheet 1; revised renderings; City review and answers
Nov. 20 Under the staff report's timeline, application materials, plat revisions and the development agreement "would need to be complete and ready for public comment" by this date. Staff report, p. 2
Nov. 22 End of the commission's 40-day period to "request more information, data, illustrations or clarifications." Staff report, p. 2
Nov. 30, 5 p.m. Written comments on the preliminary plat are due at Tetonia City Hall, P.O. Box 57, Tetonia, Idaho 83452, or by email to PZ@cityoftetonia.com. Hearing notice, p. 1
Dec. 7, 7 p.m. The city's notice sets the Planning and Zoning Commission's public hearing on the preliminary plat, 90 single-family lots and 60 townhouse lots on about 38 acres, at Tetonia City Hall, 3192 Perry Ave. Hearing notice, p. 1

2027: dates set in the records

DateWhat happenedSource
Jan. 21 Under the staff report's timeline, the date by which the commission would give its recommendation to the City Council, within 45 days of the Dec. 7 hearing. Staff report, p. 2
April 14 Deadline in the rezone and conditional use permit conditions for a subdivision application "submitted within 18 months" and "pursued in good faith." The applicant's preliminary plat application was deemed complete July 21, 2026. Staff reads the condition as requiring the subdivision plan to be "submitted and reviewed for conformance by April 2027." Notice of decision, p. 4; staff report, p. 2
May 14 Date printed in the rezone condition of Ordinance 2025-06, as provided by the city clerk: "The applicant shall submit a subdivision application for the proposed development within eighteen (18) months of the City Council's decision (5/14/2027) and shall pursue such application in good faith. If a subdivision application is not submitted within 18 months or if the subdivision application and/or approval expires, or is denied, the zoning designation of the property shall revert back to Transitional Agriculture (TA) without further action by the City." Eighteen months after the council's Oct. 14, 2025, hearing is April 14, 2027, and eighteen months after its Dec. 9, 2025, adoption of the ordinance is June 9, 2027 (DERIVED). Ordinance 2025-06, as provided by the City of Tetonia clerk, Nov. 19, 2026, second of two unnumbered pages; council minutes, Oct. 14, 2025, pp. 5-6; council minutes, Dec. 9, 2025, p. 2

2028: lease end date

DateWhat happenedSource
Dec. 31 The Water Supply Bank leases on 22-2128, 22-10835 and 22-2281, and on PFG Idaho's 22-14670, end unless released earlier. IDWR letter, Nov. 14, 2025, p. 4; IDWR letter, July 9, 2025, p. 25