Have your say
How the decision works: five requests, two city bodies
PFG Idaho, LLC and its representative, David Ferrette, have asked the City of Tetonia to approve a preliminary plat, to annex 389.25 acres, to amend the comprehensive plan and to zone the annexed land, and have filed unsigned drafts of a development agreement and an annexation agreement (hearing notice, p. 1; draft development agreement; draft annexation agreement; annexation application, p. 1; plan amendment application, p. 1). The Planning and Zoning Commission holds the public hearings on the plat, the plan amendment and the zoning and makes recommendations; the City Council makes the final decision on each request (city code 9-11-04-2(F), (G), p. 12; Idaho Code 50-222(7); 67-6509(3); 67-6511(2)(b)).
Key facts
- 5 requestsPlat, annexation, plan amendment, zoning, and the two draft agreements, counted as oneSource: hearing notice, p. 1; annexation app., p. 1; amendment app., p. 1; draft DA; draft AA
- Nov. 30Written comments due by 5 p.m.Source: hearing notice, p. 1
- Dec. 7Commission’s public hearing on the plat, 7 p.m.Source: hearing notice, p. 1
- CouncilMakes the final decision on each requestSource: city code 9-11-04-2(F), (G); Idaho Code 50-222(7); 67-6509(3); 67-6511(2)(b)
The commission holds the hearings on the plat, plan amendment and zoning; the City Council makes the final decision on each request
The Dec. 7 hearing is on the plat; after it, the council may “sustain, modify or reject” the commission’s recommendations.
Preliminary plat (SUB2025-3)
Planning and Zoning CommissionHearing Dec. 7, 2026; acts within 45 days
City CouncilMay sustain, modify or reject
Annexation (AX2026-3)
Planning and Zoning CommissionHearing depends on the 50-222 path
City CouncilEnacts an annexation ordinance
Plan amendment (AMD2026-1)
Planning and Zoning CommissionAt least one hearing; recommends
City CouncilAdopts by resolution
City zoning for the annexed land
Planning and Zoning CommissionHearing; recommends
City CouncilMay adopt or reject the ordinance
Development agreement
Planning and Zoning CommissionApproves it with the final plat
City CouncilRequires the developer to sign it
Sources: the table in the first section below, which cites city code 9-11-04-2, 9-11-04-3(K), (L), Idaho Code 50-222, 67-6509 and 67-6511. Hearing date from the hearing notice.
Show the figures as a table
| Request | Planning and Zoning Commission | City Council |
|---|---|---|
| Preliminary plat (SUB2025-3) | hearing Dec. 7, 2026; acts within 45 days | may sustain, modify or reject |
| Annexation (AX2026-3) | hearing depends on the 50-222 path | enacts an annexation ordinance |
| Plan amendment (AMD2026-1) | at least one hearing; recommends | adopts by resolution |
| City zoning for the annexed land | hearing; recommends | may adopt or reject the ordinance |
| Development agreement | approves it with the final plat | requires the developer to sign it |
What this means for the decision
- The Dec. 7 hearing is not the last step. On the plat, the City Council may “sustain, modify or reject the recommendations of the planning and zoning commission” (city code 9-11-04-2(G)(1), p. 12), and the city's contract planner wrote that for the larger proposal “the recommendation will go to City Council for another public hearing and decision” (planner’s memo, Sept. 15, 2026, p. 1).
- The city’s water ordinance, adopted Sept. 30, 2026, applies to subdivision plats and annexations and leaves the quantity and form of mitigation to the City Council (Ordinance No. 2026-09, as provided by the City of Tetonia clerk, Nov. 19, 2026, pp. 2, 4-5; details below).
- “The developer shall submit the final plat within one (1) year of preliminary plat approval; otherwise, approval of the preliminary plat and development agreement shall become null and void” (city code 9-11-04-2(G)(3), p. 13).
Have your say about this
Written comments to the Planning and Zoning Commission are due by 5 p.m. Monday, Nov. 30, 2026, and the commission takes spoken and written comments at its hearing at 7 p.m. Monday, Dec. 7 (hearing notice).
The comment helper opens with the “The development agreement” topic checked. It adds a line from the record with its source, which you can keep or delete; what you say is up to you.
How the Pinnacle Peak decision works
Each section of the record opens on its own.
In brief
PFG Idaho, LLC and its representative, David Ferrette, have asked the City of Tetonia to approve a preliminary plat for 90 single-family lots and 60 townhouse lots on about 38 acres, to annex 389.25 acres, to amend the comprehensive plan and to zone the annexed land, and have filed unsigned drafts of a development agreement and an annexation agreement (draft development agreement and draft annexation agreement, signature pages; staff report, p. 1; annexation application, p. 1; comprehensive plan amendment application, p. 1; hearing notice, p. 1). The Planning and Zoning Commission's public hearing on the plat is Monday, Dec. 7, 2026, at 7 p.m., and written comments are due by 5 p.m. Monday, Nov. 30 (hearing notice, p. 1). Under the city code and Idaho law, the commission holds the public hearings on the plat, the plan amendment and the zoning and makes recommendations, and the City Council makes the final decision on each request (city code 9-11-04-2(F), (G), p. 12; Idaho Code 50-222(7); 67-6509(3); 67-6511(2)(b)). The city's water ordinance, adopted Sept. 30, 2026, applies to subdivision plats and annexations and leaves the quantity and form of mitigation to the City Council (Ordinance No. 2026-09, as provided by the City of Tetonia clerk, Nov. 19, 2026, pp. 2, 4-5; details below).
About this page
PFG Idaho, LLC and its representative, David Ferrette, have asked the City of Tetonia to approve a preliminary plat for the first phase, to annex about 389 acres outside the city, to amend the city's comprehensive plan and to zone the annexed land, and have filed drafts of a development agreement and an annexation agreement (hearing notice, posted Nov. 18, 2026, p. 1; annexation application, p. 1; comprehensive plan amendment application, p. 1; draft development agreement; draft annexation agreement). Laws are quoted from the City of Tetonia's posted code and the Idaho Legislature's website as checked Nov. 19, 2026.
This page is general information about the approval process and is not legal advice.
The requests and the bodies that act on them
| Request | Filed | Hearing under the code or statute | Final action under the code or statute |
|---|---|---|---|
| Preliminary plat, SUB2025-3: 90 single-family lots and 60 townhouse lots on about 38 acres | Revised package submitted Oct. 9, 2026, and found complete Oct. 13, 2026 (staff report, Oct. 28, 2026, p. 4) | Planning and Zoning Commission, "one public hearing" (city code 9-11-04-2(F)(1)(b), p. 11); set for Dec. 7, 2026 (hearing notice, p. 1) | Commission acts within 45 days of the hearing; City Council may "sustain, modify or reject" the commission's recommendations (city code 9-11-04-2(F), (G), p. 12) |
| Annexation, AX2026-3: 389.25 acres | Signed Sept. 17, 2026; received Oct. 9, 2026 (annexation application, pp. 1-2) | Depends on which part of Idaho Code 50-222 applies; see annexation | City Council, by annexation ordinance (Idaho Code 50-222(7)) |
| Comprehensive plan amendment, AMD2026-1 | Form signed Feb. 9, 2026; stamped received Oct. 9, 2026 (application, p. 1) | Planning and Zoning Commission, at least one; City Council may hold one (Idaho Code 67-6509) | City Council, by resolution (Idaho Code 67-6509(3)) |
| City zoning for the annexed land: C-2, C-3, R-3 and M-2 | Listed on the annexation application, Oct. 9, 2026 (p. 1) | Planning and Zoning Commission recommends after a hearing (Idaho Code 67-6511) | City Council may "adopt or reject" the zoning ordinance amendment (Idaho Code 67-6511(2)(b)) |
| Development agreement for the first phase, and annexation agreement | Unsigned drafts, with dates left blank, in the city's application file (draft development agreement, preamble; draft annexation agreement, preamble; Teton Valley Housing agenda, Nov. 4, 2026, p. 2, item 18) | The city code takes up the development agreement with the preliminary and final plats; see the agreements | Commission approves the development agreement before the final plat goes to the council, and the council requires the developer to sign it (city code 9-11-04-3(K), (L), pp. 15-16) |
| Final plat | Follows preliminary plat approval | Commission agenda within 35 days of a complete application; the code section does not mention a hearing (city code 9-11-04-3(K), p. 15) | City Council approves a conforming plat within 30 days of its regular meeting (city code 9-11-04-3(L), p. 16) |
The city's contract planner, Ashley Koehler, described the order in a memo to the Planning and Zoning Commission on Sept. 15, 2026, before the October filings: "This application will also require an amendment to the City's Comprehensive Plan and Future Land Use Map. Under Idaho law, the Comprehensive Plan amendment must be evaluated first or concurrently with the Annexation request, as the requested zoning must align with the approved Comprehensive Plan." The same memo says the commission "will hold a public hearing where the Developer will present the full project details and the public will have the ability to provide comments," and that "the recommendation will go to City Council for another public hearing and decision" (planner's memo, Sept. 15, 2026, p. 1).
Approvals granted in 2025
The 38 acres in the first phase are in the northwest part of Tetonia city limits (hearing notice, p. 1). The city rezoned them from Transitional Agriculture to R-3 and granted a conditional use permit for single-family homes in 2025, under file ZX2025-1 (notice of decision, p. 1).
| Date | Body | Action | Source |
|---|---|---|---|
| Sept. 8, 2025 | Planning and Zoning Commission | Public hearing; voted to recommend the rezone and the permit, with conditions | notice of decision, p. 1 |
| Oct. 14, 2025 | City Council | Public hearing; approved the rezone and the permit, each 3-1, with council member Mandy Rasmussen voting no | council minutes, Oct. 14, 2025, pp. 5-6 |
| Dec. 9, 2025 | City Council | Written decision effective; rezone Ordinance 2025-06 adopted by roll call, three yes votes, with council member Aaron Hansen absent | notice of decision, p. 4; council minutes, Dec. 9, 2025, p. 2 |
| Aug. 11, 2026 | City Council | Ordinance 2026-06 corrected the parcel number in Ordinance 2025-06, three ayes and one abstention; the minutes say the action "does not change the approved rezone, conditions of approval, or the property approved by the City Council" | council minutes, Aug. 11, 2026, p. 4 |
The written decision conditions the rezone on "an application for the proposed subdivision being submitted within 18 months from the date of this approval (4/14/2027) and pursued in good faith," and provides that "If the subdivision is not applied for, denied, or the application and/or approval expires, the zone shall revert back to Transitional Agriculture (TA)" (notice of decision, p. 4).
The condition as printed in Ordinance 2025-06
The copy of Ordinance 2025-06 provided by the city clerk states the condition this way: "The applicant shall submit a subdivision application for the proposed development within eighteen (18) months of the City Council's decision (5/14/2027) and shall pursue such application in good faith. If a subdivision application is not submitted within 18 months or if the subdivision application and/or approval expires, or is denied, the zoning designation of the property shall revert back to Transitional Agriculture (TA) without further action by the City." The signature and attest lines on that copy are blank (Ordinance 2025-06, as provided by the City of Tetonia clerk, Nov. 19, 2026, second of two unnumbered pages).
The date printed in the ordinance, May 14, 2027, differs from the April 14, 2027, in the notice of decision, and from 18 months after either council date. Eighteen months after the council's Oct. 14, 2025, hearing is April 14, 2027, and eighteen months after its Dec. 9, 2025, adoption of the ordinance is June 9, 2027 (DERIVED: Oct. 14, 2025, plus 18 months; Dec. 9, 2025, plus 18 months) (notice of decision, p. 4; council minutes, Oct. 14, 2025, pp. 5-6; council minutes, Dec. 9, 2025, p. 2).
The preliminary plat, SUB2025-3
The plat filings
According to staff's Oct. 28 report, the concept plan was submitted Dec. 16, 2025, and reviewed by the commission in a work session March 2, 2026. A preliminary plat application was considered complete July 21, 2026, a revised master plan followed Aug. 10, and after further redesign "A revised Preliminary Plat application package was then submitted and considered complete on 10/13/2026" (staff report, p. 2). The application form is stamped received 10/9/26 (preliminary plat application, p. 1). The commission held a work session on the plat on Nov. 2, 2026, listed on the agenda as "Preliminary Plat review for additional information needed" (Planning and Zoning agenda, Nov. 2, 2026; planner's memo, Nov. 16, 2026, p. 5).
The commission's public hearing is Monday, Dec. 7, 2026, at 7 p.m. at Tetonia City Hall, and written comments are due by 5 p.m. Monday, Nov. 30. The notice says the commission "will evaluate the proposed preliminary plat for consistency with the City's Comprehensive Plan and applicable provisions and approval criteria of the Tetonia Land Development Code, including the Subdivision Code" (hearing notice, p. 1). The comment guide has the details.
The steps in the city code
| Step | What the code says | Source |
|---|---|---|
| Concept plan review | Before a preliminary plat is filed, the developer submits a concept plan to the city planning office, which advises the developer in writing within 10 days of the review meeting on "general conformance or nonconformance." | 9-11-04-1, p. 7 |
| Completeness | "Upon receipt of the preliminary plat with all required data as provided herein, the Administrator shall certify the application as complete and shall affix the date of application acceptance thereon." | 9-11-04-2(C), p. 10 |
| Agency review | The application goes to city departments and agencies with jurisdiction or an interest. If one does not reply in writing within 20 working days, its approval "will be considered to be granted." | 9-11-04-2(D), p. 10 |
| Commission's first review | The plat goes on the commission agenda "within forty (40) days from the date the application is certified by the Administrator as complete." The commission may request more information by letter, and the applicant has six months to comply "or the preliminary plat application shall become null and void." | 9-11-04-2(F)(1), p. 11 |
| Public hearing | "Within thirty-five (35) days from the time the preliminary plat is placed on the planning and zoning commission agenda, the planning and zoning commission shall hold one public hearing where affected and interested persons may be heard." Owners within 300 feet are notified by letter, and one notice is published in the official newspaper at least 15 days before the meeting. | 9-11-04-2(F)(1)(b), pp. 11-12 |
| Conditions for the development agreement | After the hearing, the city engineer, city attorney and other departments "shall review and recommend special conditions, including site design standards, for the development agreement," and where the development is part of a larger area, "the master plan of the entire development shall be reviewed and special conditions shall be drafted based on the master plan." | 9-11-04-2(F)(2), p. 12 |
| Commission's action | "Within forty-five (45) days from the public hearing of the proposed subdivision the planning and zoning commission shall approve, approve conditionally or disapprove the preliminary plat based on the Approval Criteria herein." The reasons are stated in writing, and the plat, the commission's findings and report, and the development agreement draft go to the City Council. | 9-11-04-2(F)(3)-(4), p. 12 |
| Council's action | "The city council shall act upon the report of the planning and zoning commission at its next regular meeting following receipt of the report. Within thirty-five (35) days the city council may sustain, modify or reject the recommendations of the planning and zoning commission." The council's reasons must specify the ordinance and standards used, the reasons for its action, and any actions the applicant could take to gain approval. | 9-11-04-2(G)(1), p. 12 |
| Extensions | "The time limits for acting on the preliminary plat may be extended by mutual consent of the developer and the planning and zoning commission and/or the city council." | 9-11-04-2(G)(2), p. 13 |
| Deadline for the final plat | "The developer shall submit the final plat within one (1) year of preliminary plat approval; otherwise, approval of the preliminary plat and development agreement shall become null and void." | 9-11-04-2(G)(3), p. 13 |
The code lists six approval criteria. They cover the surveyor's stamp and the minimum plat requirements of Idaho Code 50-1304, an owner's certificate on ownership and maintenance of roads, parks and common areas, approval of the improvement plans by city public works, the city engineer, the fire district and Idaho DEQ, a phasing plan shown on a development master plan, mitigation through the development agreement and design so that political subdivisions, "including school districts," can deliver services "without compromising quality of service delivery to current residents or imposing substantial additional costs upon current residents," and conformance with the underlying zoning, the applicable provisions of Title 9 (the land use code) and "the City's Comprehensive Plan and other applicable plans and policies" (9-11-04-2(E), pp. 10-11).
How city documents describe the plat's schedule
Staff's Oct. 28 report gives the commission's 40-day deadline to request more information as 11/22/26, says "P&Z has 35 days to hold the public hearing, which is 12/7/26 the next regularly scheduled meeting date," and says that "a 3rd meeting may be held for a recommendation to be given by P&Z to the City Council within 45 days (by 1/21/27)." The report states that the code's timelines "can be modified by mutual consent of the City and applicant," and says the Nov. 2 meeting serves "to advise the Developer on these timelines and request that a modification to these dates may be needed in order to adequately receive and incorporate service provider comments into the Plat and Development Agreement before a public hearing is scheduled" (staff report, p. 2).
The staff report's heading lists the next steps as "Public Hearing with P&Z Commission & Decision by City Council" (staff report, p. 1), and the city's application form lists "P&Z Commission review, public hearing, and recommendation" followed by "City Council review and final decision" (preliminary plat application, p. 2).
Annexation, AX2026-3
The annexation filings
The annexation application names PFG Idaho, LLC as applicant and "PFG Idaho, LLC and 862 Teton LLC" as owners, gives 389.25 acres and proposed city zoning "C2, C3, R3 and M2," marks the land as located in the Tetonia Area of City Impact, and lists "Rezone and Comp Plan Ammendment" as related applications. It is signed 9/17/2026 and stamped received 10/9/2026 (annexation application, pp. 1-2). The form tells the applicant to post a hearing notice on the property "not less than 1 week prior to the hearing," citing "City Code 9-5-4," and says the applicant pays for hearing publications and mailings and for reviews by the city's engineer, attorney and other professionals (p. 2). The applicant's narrative asks for "approval for the annexation of the 400.25-acre tract" (annexation narrative, received Oct. 9, 2026, p. 14); the application page compares the acreage figures.
City records place an earlier annexation filing in February 2026. The contract planner's Feb. 16, 2026, concept review states that "On 2/9/26 a Comp Plan Amendment application was received along with an Annexation Application of the surrounding area, but it has not been evaluated yet" (concept review memo, Feb. 16, 2026, p. 7), and her Sept. 15 memo says "The first step is for the Developer to submit a revised Annexation application to include the expanded area and proposed land uses and requested zoning" (planner's memo, Sept. 15, 2026, p. 1). The applicant's draft annexation agreement recites an application "dated as of or about January 16, 2026" (draft annexation agreement, Recital N).
Staff wrote on Oct. 28 that the comprehensive plan amendment and annexation applications received Oct. 9 had "not been fully evaluated yet," and that "This application, specifically the Comp Plan Amendment, may be necessary to support subdivision compliance" (staff report, p. 7). The city engineer has also raised annexation for parts of the first-phase street plan. An addendum from Sunrise Engineering dated Feb. 3, 2026, states that "portions of Lucas Lane, Chloe Circle and Asher Park Lane are not within the annexed area of Tetonia. These areas will need to go through the annexation process to bring in the entirety of the roadways and appurtenances" (Sunrise Engineering addendum, Feb. 3, 2026, filed with the concept review, p. 19), and the Nov. 12 review asks the applicant to "show City limits and required annexations, including the roadway areas identified in the concept addendum" (Sunrise Engineering for the city, Nov. 12, 2026, p. 5).
Idaho Code 50-222
Idaho's annexation statute sets out a general procedure and an exception for annexations with landowner consent. The current text, amended in 2026, says:
| Subsection | Text |
|---|---|
| (2)(a), consent | "'Consent' means a written document executed by the landowner or the landowner's authorized agent explicitly agreeing to annexation. Written consent to annex lands must be recorded in the county recorder's office to be binding upon subsequent purchasers, heirs, or assigns of lands addressed in the consent." |
| (3), general procedure | "Except as provided in subsection (6) of this section, no city of this state shall annex land unless and until the following requirements are met." The requirements include contiguity; notice to each landowner and the county commissioners with a consent deadline "no later than forty-five (45) days after the date of notification"; published and mailed notice "at least twenty-eight (28) days prior to the initial public hearing," on "the question of whether the subject land should be annexed and, if annexed, the zoning designation to be applied to the subject land"; a written annexation plan adopted by the council; hearings in which "the city council and the planning and zoning commission each holds a public hearing on the proposed annexation"; and consent from "Landowners representing sixty percent (60%) of the parcels and at least fifty percent (50%) of the area proposed for annexation." |
| (6)(a), annexation with consent | "In the case of a prospective annexation where all landowners of the subject property have requested annexation or where consent has been given by the landowner or landowners of a contiguous parcel or parcels or where implied consent has been given, the provisions of subsections (3) and (4) of this section shall not apply." Such land "may extend beyond the city area of impact if the land is contiguous to the city and the comprehensive plan includes the area of annexation." Once a city determines the annexation meets the subsection, it "may initiate the planning and zoning procedures set forth in chapter 65, title 67, Idaho Code, to establish the comprehensive planning policies, where necessary, and zoning classification of the lands to be annexed." |
| (7), ordinance | "If all requirements provided in subsection (3) or (6) of this section are satisfied and the city agrees to the annexation, then the city council shall enact an annexation ordinance." |
| (14), judicial review | For "a city-initiated annexation," an appeal "shall be filed by an affected person in the appropriate district court no later than twenty-eight (28) days after the date of publication of the annexation ordinance." |
Source: Idaho Code 50-222, Idaho Legislature, checked Nov. 19, 2026.
Teton County's area of city impact
The annexation application marks the land as located in the Tetonia Area of City Impact, and the draft annexation agreement states that "The Property is located within the Tetonia Area of City Impact" (annexation application, p. 1; draft annexation agreement, Recital F). Teton County set a new boundary and zoning for that area in December 2025.
The Board of County Commissioners held a public hearing on the Tetonia area of impact on Dec. 22, 2025. The minutes record that Planning Administrator Joshua Chase "stated that the proper map is exhibit B, not exhibit A," and that the board voted 3-0, with Brad Wolfe, Ron James and Dan Powers voting aye, to "Approve Ordinance 2025-1222 Tetonia Proposed AOI with the following corrections: 1. That exhibit A be changed to comply with Exhibit B; and 2. that the northerly boundary of the AOI comply with any changes being considered by the landowners." During public comment a speaker raised a property dispute along the northern part of the area, and Chase "clarified that the AOI boundary must follow property lines per Idaho statute" (Board of County Commissioners minutes, Dec. 22, 2025, pp. 8-9).
The copy of Ordinance 2025-1222 posted on the county's website replaces Title 7, Chapter 2 of the county code, the land development code for the Tetonia area of impact, and is headed "Adopted December 22, 2025" (posted ordinance, p. 1). Its signature page bears signatures on the lines for the three commissioners and the county clerk, but the day in "this ____ day of December, 2025" and the line "Published: ____" are blank. Section 5 provides that "The Tetonia AOI shall be reconsidered again on or before December 22, 2030" (p. 2). The attached code is headed "Adopted December 22, 2025, Effective January 14, 2026" (p. 3). The copy includes a map titled "Tetonia Area of Impact (adopted December 22, 2025)" (p. 8), and its zone table sets a minimum lot size of 2.5 acres in the AOI-2.5 district (p. 9).
Teton County's GIS layers, checked Nov. 19, 2026, show the following for two parcels in the plan area. These are the county's mapping data, not a survey or a legal description of the boundary.
| Parcel | Owner and size in the county parcel layer | Where the county's layers place it |
|---|---|---|
| RPC00000291201, the first-phase plat land (hearing notice, p. 1) | PFG Idaho LLC; SW4NE4, Section 29; 40 acres listed | Inside Tetonia city limits; not in the area of impact |
| RP06N45E290011 | 862 Teton LLC; N2NE4 and NW4, Section 29; 233.78 acres listed | Inside the area of impact, in the county's Tetonia "AOI-2.5 (2.5-ac min lot size)" zone. By our overlay of the county's parcel and zoning polygons, more than 99.9 percent of the parcel's mapped area falls in that zone. |
Sources: Teton County parcel layer, city limits and impact-area layer and area of impact zoning layer, Teton County GIS, checked Nov. 19, 2026. Other parcels in the plan area were not part of the GIS results used for this page.
Comprehensive plan amendment, AMD2026-1
The amendment filings
The application form, filed by David Ferrette as developer, is signed 2-9-2026 and stamped "RECEIVED 10-9-2026" (comprehensive plan amendment application, p. 1). The comprehensive plan amendment narrative, dated Oct. 9, 2026, says that "In conjunction with our recent annexation submittal, PFG Idaho LLC is formally applying to amend specific sections of the 2009 Tetonia Comprehensive Plan." It asks that the plan's commercial pattern along Highway 33 "be extended to available land on the north and west sides of town," and that the land use map be revised because "The current Land Use Map does not reflect our proposed annexation" (comprehensive plan amendment narrative, p. 2).
Staff wrote on Oct. 28 that "the City is processing its own update to the 2009 Comp Plan and it may be advised that this project also be reviewed using the proposed new City Comp Plan" (staff report, p. 7), and the commission's Nov. 2 agenda lists a work session on "Comprehensive Plan Amendment- review draft & FLUM. Applicant- City of Tetonia" (Planning and Zoning agenda, Nov. 2, 2026).
Idaho Code 67-6509
- Commission hearing: the commission, "prior to recommending the plan, amendment, or repeal of the plan to the governing board, shall conduct at least one (1) public hearing in which interested persons shall have an opportunity to be heard."
- Notice: "At least fifteen (15) days prior to the hearing, notice of the time and place and a summary of the plan to be discussed shall be published in the official newspaper or paper of general circulation within the jurisdiction." Notice also goes, at least 15 days before the commission's hearing, "to all political subdivisions providing services within the planning jurisdiction, including school districts" and the manager of the local public airport.
- Changes after the hearing: if the commission recommends "a material change to the proposed amendment," it gives notice and holds another hearing unless the governing board will hold one.
- Council hearing: the governing board, "as provided by local ordinance," "may conduct at least one (1) public hearing, in addition to the public hearing or hearings conducted by the commission." It "shall not hold a public hearing, give notice of a proposed hearing, nor take action upon the plan, amendments, or repeal until recommendations have been received from the commission."
- Adoption: "No plan shall be effective unless adopted by resolution by the governing board."
- Who may ask: "Any person may petition the commission or, in absence of a commission, the governing board for a plan amendment at any time, unless the governing board has established by resolution a minimum interval between consideration of requests to amend, which interval shall not exceed six (6) months."
Source: Idaho Code 67-6509, Idaho Legislature, checked Nov. 19, 2026.
City zoning for the annexed land
The zoning request
The zoning request is filed with the annexation. The annexation application proposes city zoning of "C2, C3, R3 and M2" (annexation application, p. 1), and the "Annexation & Rezone Narrative" assigns 107.77 acres to R-3, 104.45 to C-2, 28.68 to M-2 and 159.35 to C-3 (annexation narrative, p. 6). The draft annexation agreement would have the city "initially approve land use zones" for each owner's parcel, and provides that "Prior to annexation, the City shall request and receive the recommendation of its planning and zoning commission on the proposed comprehensive plan and zoning ordinance changes for the Property, and the City and its commission shall follow the notice-and-hearing procedures provided in Idaho Code § 67-6509" (draft annexation agreement, § 3).
Idaho Code 67-6511
- Zoning by ordinance: the governing board establishes zones "by ordinance adopted, amended, or repealed in accordance with the notice and hearing procedures provided under section 67-6509," and "The zoning districts shall be in accordance with the policies set forth in the adopted comprehensive plan."
- Where requests go: "Requests for an amendment to the zoning ordinance shall be submitted to the zoning or planning and zoning commission," and "Particular consideration shall be given to the effects of any proposed zone change upon the delivery of services by any political subdivision providing public services, including school districts, within the planning jurisdiction."
- Who acts: "After considering the comprehensive plan and other evidence gathered through the public hearing process, the zoning or planning and zoning commission may recommend and the governing board may adopt or reject an ordinance amendment."
- Notice of a zoning boundary change: by mail "to property owners or purchasers of record within the land being considered, and within three hundred (300) feet of the external boundaries of the land being considered," and "posted on the premises no less than one (1) week prior to the hearing." Where notice would go to 200 or more owners, a city may use an alternative set by ordinance or, without one, a display advertisement "at least fifteen (15) days prior to the hearing date" plus site posting.
- Conflict with the plan: if the governing board finds a request in conflict with the adopted plan, it may require the request to be submitted to the commission or, where there is no commission, consider a plan amendment itself, and "After the plan has been amended, the zoning ordinance may then be considered for amendment."
Source: Idaho Code 67-6511, Idaho Legislature, checked Nov. 19, 2026.
The development agreement and the annexation agreement
The draft agreements
Staff wrote that all required plat materials, which the code says include a development agreement, were submitted Oct. 9, and that "The Development Agreement is pending further review. More details in regards to the required improvements and Improvement Plans are needed before a D.A. can be finalized" (staff report, p. 4). The city engineer wrote on Nov. 12 that "The draft development agreement is received; detailed review of that document will follow separately" (Sunrise Engineering, Nov. 12, 2026, p. 1). The draft development agreement covers the 150-lot first phase and states that it "shall become valid and binding only upon its approval by the City Council and its recording with the City Clerk and Teton County Recorder's Office" (draft development agreement, § 43). The draft annexation agreement says its terms "will be incorporated by reference into the Annexation Ordinance" (draft annexation agreement, § 2). The terms of both drafts are on the application page.
The development agreement in the city code
- With the preliminary plat: "A development agreement template shall be provided by the city. It is the responsibility of the developer to address general and specific conditions relative to the proposed development based on the city's format and submit an electronic and paper copy as part of the preliminary plat process" (9-11-04-2(B)(5), p. 10).
- After the commission's hearing, staff recommend special conditions for the agreement, and the commission sends "the development agreement draft" to the council with the plat (9-11-04-2(F)(2)-(4), p. 12).
- With the final plat: the commission consults the city engineer and city attorney "in order to finalize the development agreement specific to the proposed subdivision," and "The final plat shall not be submitted to the city council until the planning and zoning commission approves a development agreement" (9-11-04-3(K)(2), p. 15).
- The council considers "the final plat and development agreement," and "shall, as a condition precedent to the approval of any final plat, require the developer to sign a development agreement" (9-11-04-3(L), pp. 15-16).
Idaho Code 67-6511A
The state statute on development agreements provides that "Each governing board may, by ordinance adopted or amended in accordance with the notice and hearing provisions provided under section 67-6509, Idaho Code, require or permit as a condition of rezoning that an owner or developer make a written commitment concerning the use or development of the subject parcel." It continues: "Such commitments shall be recorded in the office of the county recorder and shall take effect upon the adoption of the amendment to the zoning ordinance." A commitment "may be modified only by the permission of the governing board after complying with the notice and hearing provisions of section 67-6509," and may be terminated, "and the zoning designation upon which the use is based reversed," upon failure of its requirements after notice and hearing. The statute adds that "By permitting or requiring commitments by ordinance the governing board does not obligate itself to recommend or adopt the proposed zoning ordinance" (Idaho Code 67-6511A, checked Nov. 19, 2026). The applicant's draft annexation agreement cites Idaho Code sections 50-1030, 67-6511A, 67-8209 and 67-8214 as authority for its hook-up fee credit (draft annexation agreement, § 5.5).
A school site
Teton School District #401's revised letter to the city, dated Nov. 11, 2026, repeats its request for a voluntary $164,340 contribution and adds: "Given the size of this development and its request to be annexed within the City of Tetonia, the school district also requests that a portion of land be dedicated to a potential future school site. An appropriate size for the forecasted growth of Tetonia would be five acres" (school district letter, Nov. 11, 2026, p. 1, p. 2). The phasing map attached to the applicant's draft annexation agreement as Exhibit F labels an area "10 ACRES PUBLIC SCHOOL," with the note "School Will come online when needed" (draft annexation agreement, Exhibit F). Neither draft agreement's text mentions schools; the application page compares the narratives' school commitments with the drafts.
The final plat
Under the city code, after a preliminary plat is approved or conditionally approved, the developer "may cause the subdivision master plan, or part thereof, to be surveyed and a final plat prepared in accordance with the preliminary plat as approved or conditionally approved" (9-11-04-3(A), p. 13).
| Step | What the code says | Source |
|---|---|---|
| Changes from the preliminary plat | If the final plat does not conform to the approved preliminary plat, the city assigns it to the commission agenda "for its action as a preliminary plat." | 9-11-04-3(I)(3), p. 15 |
| Agency review | Departments and agencies that do not reply in writing within 15 days are considered to have approved. | 9-11-04-3(J), p. 15 |
| Commission | The final plat goes on the commission agenda "within thirty-five (35) days from the date the application is certified by the administrator as complete," and the commission finalizes and approves the development agreement. | 9-11-04-3(K), p. 15 |
| Council | "If the final plat and development agreement conforms to the requirements of this Title and the Idaho Code, the city council shall approve the plat within thirty (30) days after the date of the regular meeting." The council accepts the dedications shown on the plat. | 9-11-04-3(L), p. 16 |
| Signatures on the plat | Certifications of approval by the city engineer, the county engineer, the commission, the City Council and the fire marshal, and of recording by the county recorder. | 9-11-04-3(H), p. 14 |
| Guarantee of improvements | "As a condition for granting approval of the final plat," the developer guarantees construction of all required improvements "within two (2) years of final plat approval unless extended one year by mutual consent," in an amount of "one hundred fifty percent (150%) of estimated cost as determined by the city engineer." | 9-11-08-1(D), p. 29 |
| Recording | "The final plat shall be filed with the county recorder within one (1) year after approval by the city council, otherwise such approval of the final plat and development agreement shall become null and void." | 9-11-04-3(M), p. 16 |
The contract planner's Nov. 16 memo notes that "A financial guarantee is also required to be submitted during the Final Plat" (planner's memo, Nov. 16, 2026, p. 6).
Water rights and the city's water ordinance
Ordinance 2026-09
At its Sept. 8, 2026, meeting, the City Council heard from the city engineer, who "suggested Tetonia change the Title 7, Drinking Water code to require new developments to contribute water rights as new growth comes"; the mayor recommended bringing it to a later meeting "so that it can be officially noticed and so that the actual draft wording can be presented," and no motion was made (council minutes, Sept. 8, 2026, p. 3).
On Sept. 30, 2026, the council held a public hearing on "Title 7 Code Amendment, Drinking Water Capacity and Water Rights Requirements for Future Development, Proposed Ordinance 2026-09," at which no member of the public asked to comment. The minutes record that "Ordinance details were reviewed and discussion regarding how drinking water rights could be required for future development impacts. More discussion was made regarding protecting the City infrastructure so that development pays for itself." The council approved the ordinance by roll call, with Councilmembers Kody Hill, Mandy Rasmussen and Blaine Ball voting yes and council member Aaron Hansen absent (council minutes, Sept. 30, 2026, p. 1).
The Oct. 28 staff report and the Nov. 16 planner's memo say that "the City does not have the water capacity to service this subdivision without mitigation" and that "The City recently adopted a Water Source Capacity and Water Rights Mitigation Ordinance that requires the Developer to provide specific water use information for further analysis" (staff report, p. 6; planner's memo, p. 6). The city engineer's Nov. 12 review asks the applicant for "a Water Rights Mitigation Plan under the adopted ordinance," says "The City Engineer will recommend the mitigation for Council approval," and states that "Any deferral requires a Council-approved agreement with security and interim protections. Required capacity must be available before connections are released" (Sunrise Engineering, Nov. 12, 2026, p. 3). The applicant answered on Nov. 19 that the mitigation plan "will be provided upon receipt of the City’s adopted ordinance. This document has been requested by PFG buy [sic] has not yet been provided," and that "Applicant understands that no connections can be made until additional water rights are received and a well is installed" (response worksheet, pp. 7-8).
What the text of Ordinance 2026-09 says
The copy of Ordinance No. 2026-09 provided by the city clerk is titled "Water Source Capacity and Water Rights Mitigation Requirements." It states that the council passed it and the mayor approved it on Sept. 30, 2026; the signature and attest lines on this copy are blank (Ordinance No. 2026-09, as provided by the City of Tetonia clerk, Nov. 19, 2026, pp. 1, 5). It is not yet posted with the documents on this site.
| Section | Text | Page |
|---|---|---|
| § 3, applicability | "This Ordinance shall apply to any Development requesting: 1. A connection to the municipal water system; 2. Approval of a subdivision plat; 3. Annexation accompanied by a request for municipal water service; 4. Site plan approval for commercial, industrial, institutional, or multifamily development; or 5. Any other approval determined by the City to increase demand on the municipal water system." The ordinance defines "Development" as "Any subdivision, planned unit development, multifamily development, commercial development, industrial development, annexation, or other project that results in additional demand upon the municipal water system." | pp. 1-2 |
| § 4.B, threshold and phasing | "Water source capacity mitigation shall be required for developments that create or are estimated to create demand exceeding two (2) Equivalent Dwelling Units (EDUs) or all annexations." "The City Engineer shall determine the number of EDUs attributable to a proposed development for purposes of preparing the written impact assessment and recommendation required under this Ordinance." "When a phased development is proposed, all phases of the project shall be considered together when determining whether the mitigation threshold has been met." | p. 2 |
| § 4.D, mitigation plan | "Applicants subject to this Ordinance shall submit a Water Rights Mitigation Plan identifying mitigation measures sufficient to offset the development's impact on municipal water source capacity." The ordinance defines the plan as one "identifying the source, quantity, and method by which water source impacts caused by a proposed development will be mitigated." | pp. 2-3 |
| § 4.E, options | "Developments exceeding the mitigation threshold shall provide one or more of the following mitigation measures as approved by the City Council: 1. Convey acceptable water rights to the City; 2. Convey canal shares or other water assets acceptable to the City; 3. Fund acquisition of water rights by the City; 4. Construct water supply improvements that increase source capacity or reliability; 5. Implement water conservation measures approved by the City; 6. Pay an in-lieu mitigation fee established by City Council Resolution; or 7. Provide another mitigation alternative determined by the City Council to provide an equivalent benefit to the municipal water system." The ordinance defines "Water Assets" as "Groundwater rights, surface water rights, canal company shares, storage rights, mitigation rights, leased water rights, or other water-related interests approved by the City." | pp. 2-3 |
| § 4.F, in-lieu fee | "Developments creating more than two (2) EDUs but fewer than twenty-five (25) EDUs may satisfy all or a portion of the mitigation requirement through payment of an in-lieu water source capacity mitigation fee." "The fee shall be established by City Council Resolution and shall reasonably reflect the City's estimated cost of acquiring additional water rights, water assets, or water supply improvements necessary to offset the impacts of new development." The copy states no fee amount. | p. 3 |
| § 7, timing | "All required mitigation shall be completed prior to: 1. Recording of a final subdivision plat; 2. Issuance of a building permit; or 3. Final Approval of a Conditional Use Permit; or 4. Such later date approved through a Development Agreement authorized by the City Council." Under § 8, the council "may approve a Development Agreement establishing a phased mitigation schedule" where it finds that "The public interest will be served," "Adequate interim protections exist," "Adequate security is provided" and "The agreement reasonably ensures completion of all mitigation obligations." | p. 4 |
| § 9, who decides | "The City Engineer shall review all Water Rights Mitigation Plans and prepare written recommendations for consideration by the City Council." "The City Council shall retain final authority to determine: 1. Whether mitigation is required; 2. The quantity and form of mitigation required; 3. Acceptance of water rights, water assets, in-lieu fees, or alternative mitigation measures; 4. Approval of Development Agreements; and 5. Any waiver, modification, or adjustment authorized by this Ordinance." Under § 6.B, "The City Engineer's recommendation shall be advisory in nature and shall be forwarded to the Planning and Zoning Commission and City Council as part of the development review process." | pp. 4-5 |
| § 12, effective date | "This Ordinance shall be in full force and effect upon passage, approval, publication, and recording according to law." The copy shows no publication or recording date. | p. 5 |
Source: Ordinance No. 2026-09, as provided by the City of Tetonia clerk, Nov. 19, 2026, pages as listed. The copy contains no provision that addresses applications filed before Sept. 30, 2026.
Changing a water right: Idaho Code 42-222
Under Idaho Code 42-222, the director of the Idaho Department of Water Resources approves or denies a change to a water right's point of diversion, place, period or nature of use. The water rights page lists the rights on the Pinnacle Peak land and IDWR's records on them.
- Application: a water right holder "who shall desire to change the point of diversion, place of use, period of use or nature of use of all or part of the water, under the right shall first make application to the department of water resources for approval of such change."
- Protests: the department's notice "shall advise that anyone who desires to protest the proposed change shall file notice of protests with the department within ten (10) days of the last date of publication." On a protest, the director investigates and holds a hearing. With or without a protest, the director does not decide until receiving the watermaster's recommendation.
- Criteria: the director approves a change "in whole, or in part, or upon conditions, provided no other water rights are injured thereby, the change does not constitute an enlargement in use of the original right, the change is consistent with the conservation of water resources within the state of Idaho and is in the local public interest." The statute adds that "The director shall not approve a change in the nature of use from agricultural use where such change would significantly affect the agricultural base of the local area."
- Municipal use: "When the nature of use of the water right is to be changed to municipal purposes and some or all of the right will be held by a municipal provider to serve reasonably anticipated future needs, the municipal provider shall provide to the department sufficient information and documentation to establish that the applicant qualifies as a municipal provider and that the reasonably anticipated future needs, the service area and the planning horizon are consistent with the definitions and requirements specified in this chapter."
- Review: a person aggrieved by the department's decision may seek judicial review "if a protest was filed and a hearing held thereon"; if not, the applicant may request a hearing first.
Source: Idaho Code 42-222, Idaho Legislature, checked Nov. 19, 2026.
Municipal water terms: Idaho Code 42-202B
| Term | Definition |
|---|---|
| Municipal provider | Includes "A municipality that provides water for municipal purposes to its residents and other users within its service area" (subsection 5(a)); a municipality includes "a city incorporated under section 50-102, Idaho Code" (subsection 4). |
| Municipal purposes | "water that a municipal provider is entitled or obligated to supply to users within a service area, including those located outside the boundaries of a municipality served by a municipal provider, for residential use, commercial use, industrial use, irrigation of parks and open spaces, geothermal heating and cooling, and related purposes, or a combination thereof" (subsection 6(a)). |
| Reasonably anticipated future needs | "future uses of water by a municipal provider for municipal purposes within a service area which, on the basis of population and other planning data, are reasonably expected to be required within the planning horizon of each municipality within the service area not inconsistent with comprehensive land use plans approved by each municipality" (subsection 8). |
| Service area | For a city, it "shall correspond to its corporate limits, or other recognized boundaries, including changes therein after the permit or license is issued," and may include areas outside those limits "within the municipality's established planning area if the constructed delivery system for the area shares a common water distribution system with lands located within the corporate limits" (subsection 9). |
| Local public interest | "the interests that the people in the area directly affected by a proposed water use have in the effects of such use on the public water resource" (subsection 3). |
Source: Idaho Code 42-202B, Idaho Legislature, checked Nov. 19, 2026.
Written decisions and reconsideration
Idaho Code 67-6535 governs decisions on land use applications under the Local Land Use Planning Act. It requires that "The approval or denial of any application required or authorized pursuant to this chapter shall be in writing and accompanied by a reasoned statement that explains the criteria and standards considered relevant, states the relevant contested facts relied upon, and explains the rationale for the decision based on the applicable provisions of the comprehensive plan, relevant ordinance and statutory provisions, pertinent constitutional principles and factual information contained in the record."
"Any applicant or affected person seeking judicial review of compliance with the provisions of this section must first seek reconsideration of the final decision within fourteen (14) days. Such written request must identify specific deficiencies in the decision for which reconsideration is sought." A written decision on reconsideration is due "within sixty (60) days of receipt of the request for reconsideration or the request is deemed denied." An applicant denied an application or aggrieved by a final decision on matters identified in section 67-6521(1)(a) "may, within twenty-eight (28) days after all remedies have been exhausted under local ordinance, seek judicial review" (Idaho Code 67-6535, checked Nov. 19, 2026).
The city's written decision on the 2025 rezone became effective Dec. 9, 2025, and carried an appeal notice (notice of decision, p. 4). At its Jan. 13, 2026, meeting, the council heard from City Attorney Bart Birch that a request for reconsideration had been made Dec. 24, 2025, and that he "confirmed that the request was untimely"; the council voted, three ayes and one abstention, "to not entertain the request for reconsideration" (council minutes, Jan. 13, 2026, pp. 2-3).
Anyone considering a request for reconsideration, an appeal or a water right protest should consult a lawyer licensed in Idaho.
Laws cited on this page
Each was checked on Nov. 19, 2026.
- Tetonia City Code, Title 9, Chapter 11 (subdivision), as amended in 2024, City of Tetonia
- Idaho Code 50-222, annexation by cities
- Idaho Code 67-6509, comprehensive plan adoption and amendment
- Idaho Code 67-6511, zoning ordinance
- Idaho Code 67-6511A, development agreements
- Idaho Code 67-6535, written decisions and reconsideration
- Idaho Code 42-222, changes to water rights
- Idaho Code 42-202B, water definitions