The issues
Questions the record doesn’t answer yet
For each of seven questions about the Pinnacle Peak proposal, “What the record says” gives the facts in the public records, each linked to the document and page. Where the applicant’s own filings address a question, this page quotes them. “What it doesn’t” names what we did not find in the documents we checked, and which documents those were.
The record means the documents posted on this site’s Documents page, as of Nov. 19, 2026, plus the city ordinances the clerk provided that day. A gap here may be filled by a record we do not have; if you know of one, tell us at the end of the page.
Key facts
- 7Questions the records on this site don’t answer yetSource: the questions below
- 12 daysFrom the posted notice, Nov. 18, to the comment deadline, Nov. 30Source: hearing notice, p. 1
- 674 pagesIn the four KLOA traffic studies in the application (our count)Source: question 6
- 1,504 pagesIn the 127 PDF files on this site’s Documents page (our count)Source: Documents
12 days to send written comments, with Thanksgiving in between
Written comments are due by 5 p.m. Monday, Nov. 30; the commission also takes spoken and written comments at its hearing at 7 p.m. Monday, Dec. 7.
Sources: hearing notice, p. 1. 12 days is Nov. 30 minus Nov. 18. One tick per day.
Show the dates as a table
| Step | Date | Source |
|---|---|---|
| Hearing notice marked posted | Wed., Nov. 18, 2026 | hearing notice, p. 1 |
| Thanksgiving | Thu., Nov. 26 | |
| Written comments due | 5 p.m. Mon., Nov. 30 | hearing notice, p. 1 |
| Public hearing; spoken and written comments taken | 7 p.m. Mon., Dec. 7 | hearing notice, p. 1 |
What this means for the decision
- Written comments are due by 5 p.m. Monday, Nov. 30, and “Verbal and written comments will also be accepted during the public hearing” on Dec. 7 (hearing notice, p. 1).
- The notice says: “Information pertinent to this application is available for public review upon request at Tetonia City Hall or by emailing clerk@cityoftetonia.com” (hearing notice, p. 1).
- The city engineer’s “detailed review” of the draft development agreement “will follow separately” (engineer’s review, p. 1); it is not among the records on this site.
- The Dec. 7 hearing is not the last step: on the plat, the City Council may “sustain, modify or reject the recommendations of the planning and zoning commission” (city code 9-11-04-2(G)(1), p. 12).
Have your say about this
Written comments to the Planning and Zoning Commission are due by 5 p.m. Monday, Nov. 30, 2026, and the commission takes spoken and written comments at its hearing at 7 p.m. Monday, Dec. 7 (hearing notice).
The comment helper offers topics from the record, each with its source, which you can keep or delete; what you say is up to you.
The seven questions
Question 1 of 7Where would tournament teams and their families stay, and how would they get here?
What the record says
- The baseball resort’s traffic study describes weekly tournaments for 20 teams of about 13 players and three coaches, Monday through Saturday from Memorial Day weekend to Labor Day weekend. Players and coaches stay at an on-site camp, and the baseball resort would have “a RV park for players/families should they travel to the park in a RV” (KLOA resort study, Aug. 19, 2026, p. 12).
- The resort study says teams “are national and will primarily arrive from driving a personal vehicle or flying to the area and renting a vehicle,” and that spectators “will consist of the family members of players” (p. 12).
- It estimated the direction of resort traffic “based on the locations of existing hotel accommodations”: 60 percent to and from the southeast, 20 percent west on Highway 33 and 20 percent north on Highway 32. It adds that this “does not take into consideration the potential for future hotel accommodations to be provided as part of the Pinnacle Peak masterplan development” (p. 13).
- KLOA’s master plan study lists “A hotel with 120 rooms” in Zone 1, which it assigns to Phase II, and says that as of February 2026 “only the first two phases of the development are identified” (KLOA master plan study, Oct. 9, 2026, p. 17).
What the applicant’s filings and the resort say
- The annexation narrative describes the resort as “anchored by nationally-themed tournament fields, team lodging, and family amenities,” says “Tournament weeks will fill the complex with visiting families who need lodging, meals, fuel, and retail services,” and projects more than $477,000 a year in revenue for Tetonia: “The largest chunk will be from Tetonia’s 5% fee on lodging, charged to each week’s participants” (annexation narrative, p. 8). The plan amendment narrative says the complex will draw “visiting teams, families, and spectators traveling Highway 33, together with the lodging, dining, and travel services those visitors require,” and that “hotel and motel use is permitted in C-3,” the highway business zone it describes for that use (plan amendment narrative, p. 5).
- The resort’s website lists “Player & Coach Lodging with Meals included” (pricing page, archived Nov. 19, 2026). Its FAQ answers the question “Will there be enough housing nearby for the families of the players?” with: “Our customers will actually create a more predictable and sustainable reservation cycle for local hotels compared with last-minute bookings (based on conversations with hotel owners). Tetonia has a 5% local option tax on short-term rentals and hotels so the community will benefit greatly from families staying locally” (FAQ page, archived Nov. 19, 2026). Its trip-planning page gives drive times to the resort from airports at West Yellowstone (45 minutes), Jackson Hole (50 minutes) and Idaho Falls (70 minutes) (trip-planning page, archived Nov. 19, 2026; the times are in the page’s map image, checked Nov. 19, 2026). Its construction updates say the resort is “exploring high-quality temporary lodging accommodations as a contingency plan” if team lodging is not finished for opening day (construction updates, archived Nov. 19, 2026).
What it doesn’t
- The resort study counts vehicles, one per player, with coaches and spectators assumed to ride along; it gives no count of family members or other visitors in a tournament week (KLOA resort study, pp. 12, 14).
- None of the three traffic studies, the annexation narrative or the two draft agreements names the hotels or short-term rentals that visiting families would use, or counts the existing hotel rooms or rentals in or near Tetonia; the resort study refers to “the locations of existing hotel accommodations” without listing them.
- None of them gives a year for the 120-room hotel. The master plan study puts full buildout in 2045 without dating each phase (p. 17).
- The text of the three traffic studies does not mention the airports named on the resort’s website.
Question 2 of 7What would the traffic mean for Highway 33, the Pass, the Ashton–Tetonia Trail and traffic headed for the national parks?
What the record says
- KLOA’s master plan study analyzed 10 intersections: Highway 33 at Highway 32 and at both ends of N 3000 W, Main Street (Highway 33 in town) at Jackson, Teton, Central, Perry and Leigh avenues, Highway 33 at Egbert Avenue/Jorgensen Street, and Egbert Avenue at N 3000 W (KLOA master plan study, p. 4).
- Traffic was counted on Thursday, Dec. 11, and Saturday, Dec. 13, 2025, and the counts were “increased by 52 percent to reflect the peak season which occurs in July” (KLOA resort study, pp. 8-9). Highway 33 carries an average of 3,700 vehicles a day west of Highway 32, 5,100 between Highway 32 and the south leg of N 3000 W, and 5,900 east of it, citing Idaho Transportation Department 2024 figures (KLOA master plan study, p. 10).
- For the homes and businesses in the master plan, the master plan study sends 65 percent of trips to and from the southeast of Tetonia, 30 percent west on Highway 33 and 5 percent north on Highway 32 (p. 19). For the resort, the split is 60, 20 and 20 percent (KLOA resort study, p. 13).
- With the full master plan built, in 2052, the resort study finds the southbound Highway 32 approach to Highway 33 at level of service F in three of four peak hours and the side streets at Highway 33 at E or F “during a majority of the peak hours.” It attributes the side streets’ level of service F to the peak-season adjustment and regional growth and says those levels of service “are not a result of the traffic estimated to be generated by the proposed baseball resort” (p. 22; see the baseball resort page). The master plan and resort studies recommend watching Highway 33 volumes to see whether a regional study is warranted “to determine the need to widen” it to two lanes each way (KLOA master plan study, p. 5; KLOA resort study, p. 24).
- The Idaho Transportation Department wrote on Aug. 24, 2026, that “Signals are required at Lucas Lane, Chloe/Asher, and Perry Ave given the traffic impacts to the highway” (ITD email, p. 1), and that the Highway 33 and Highway 32 intersection “will need to be evaluated for turn lanes and a signal warrant” (ITD email, p. 1). The city planner’s Nov. 16 memo lists ITD’s comments as “Pending. Applicant needs to pursue” (planner’s memo, p. 1). Staff wrote that “The traffic studies, encroachment permits, and mitigation agreements should be completed prior to any recommendation from P&Z” (staff report, Oct. 28, 2026, p. 8).
- The master plan’s roads “will not cross the Ashton-Tetonia Trail” (KLOA master plan study, p. 3), and the trail “has an unmarked crossing with State Route 33” inside the study area (p. 13). On Oct. 9, 2026, the Idaho Department of Parks and Recreation rejected “a one-time payment of $6,600.00 for three easements crossing the ATT” and asked for the developer’s traffic study (IDPR letter, p. 1). Staff wrote that “neither the Developer nor the City has an easement from Idaho State Parks to cross the Rail Trail for utilities and/or roads” (staff report, p. 5). The applicant’s Nov. 19 answers say “City is responsible for coordination and obtaining necessary easements and permits for crossing Rails-to Trails. If not secured, access from Hwy 33 and Egbert Ln will be required” (response worksheet, p. 12). The contract planner had recommended “that the Developer obtain the required Rail Trail easements before the subdivision proceeds to ensure the proposed street connections can be installed as shown” (planner’s memo, Nov. 16, 2026, p. 7).
What the applicant’s filings say
- The annexation narrative says, “We are actively working with the Idaho Transportation Department to obtain the necessary access approvals” (annexation narrative, p. 11), and the plan amendment narrative says, “ITD is requiring the installation of two traffic lights along Highway 33 to control traffic” (plan amendment narrative, p. 5).
- The master plan study says “Additional traffic studies will be completed as part of each of the development phases” and will “determine at what phase the identified improvements will be required” (KLOA master plan study, p. 5).
What it doesn’t
- The three traffic studies do not mention Teton Pass, Yellowstone or Grand Teton National Park, and Driggs and Victor appear in them only as place names on each study’s location map (Figure 1; KLOA master plan study, p. 7). None analyzes a road or intersection outside its study area in and next to Tetonia.
- None of them estimates how many trips are headed to or from the national parks; each assigns trips only by direction (southeast, west, north).
- The trail’s unmarked crossing of Highway 33 is not one of the intersections where traffic was counted or analyzed (KLOA master plan study, pp. 4, 13).
- No response from ITD to the revised traffic studies dated Sept. 11 and Oct. 9, 2026, is among the records on this site; ITD’s two posted emails are dated Aug. 24, 2026.
Question 3 of 7Who pays if sewer or water capacity runs short before mitigation is complete?
What the record says
- City staff wrote that “the City does not have the water capacity to service this subdivision without mitigation” (staff report, p. 6).
- The city engineer lists sewer thresholds from the city’s wastewater study: a third aerator at 289 equivalent residential units (88 above the study’s 201) and an additional treatment lagoon cell at 339 (138 above it). “These limits apply to the entire City system, not just Pinnacle Peak.” The engineer asks the applicant to “identify the developer’s proposed share of City sewer improvements” and to “Establish costs, responsibilities, completion dates, and phase limits in the development agreement, separating project needs from existing deficiencies and other future growth” (engineer’s review, Nov. 12, 2026, p. 2).
- On water, the engineer writes: “Any deferral requires a Council-approved agreement with security and interim protections. Required capacity must be available before connections are released” (p. 3), and “Preliminary plat approval does not reserve capacity for all 150 units. Confirm capacity and completed mitigation before service” (p. 5).
- The applicant’s Nov. 18 reports list 0 water and 88 sewer equivalent residential units available before upgrades and say Phase 3 “will exceed the 88 available ERU’s. A new aerator will be needed” (water report, p. 3; sewer report, pp. 3-4). On its share of city sewer improvements, its Nov. 19 response worksheet says “Additional research will be needed to establish costs, shared responsibilities, and completion dates” and “The DA won’t be signed until the Final Plat is recorded. We have time to resolve this issue” (response worksheet, p. 6).
- Ordinance 2026-09 states: “Approval of a development application shall not create a vested right to municipal water service unless and until all applicable mitigation requirements have been satisfied and the City determines that adequate capacity remains available to serve the development.” A phased mitigation schedule needs a council-approved development agreement with “Adequate security” (Ordinance No. 2026-09, as provided by the City of Tetonia clerk, Nov. 19, 2026, §§ 6.E, 8, p. 4; other provisions quoted on the approvals page).
What the applicant’s filings say
- The draft development agreement says the developer “shall construct all Improvements at its sole cost and expense” (§ 2), and the draft annexation agreement says the owners “intend, at their sole cost and expense,” to build “certain public water and sanitary sewer mains, lines, and related facilities” (§ 5.1). The draft development agreement would also bar building permits in a subphase until the off-site improvements needed for its water and sewer service are substantially complete (§ 11), and would require a letter of credit or performance bond for 125 percent of each subphase’s projected improvement costs (§ 13). Both drafts would credit 75 percent of water and sewer connection and impact fees until the developer’s “Recoverable Infrastructure Costs” are repaid (draft development agreement, §§ 2, 4.2; draft annexation agreement, §§ 5.1, 5.5; see the land use page).
- In August the city engineer wrote that “All off-site sewer utility costs will be at the development expense” (Sunrise Engineering, Aug. 20, 2026, p. 2). The applicant’s engineer answered: “A sewer extension to the specified intersection will be provided, provided that matching existing city sewer depths remains feasible upon final design,” and that where those depths are not feasible, “sewer will be routed to proposed lift station” (Eagle Rock Engineering responses, p. 3).
- The annexation narrative says the developer “will convey water rights and construct new wells sufficient not only to serve the annexed land, but to provide additional capacity for the City of Tetonia beyond the project boundary,” that “Pinnacle Peak will convey a full 1.0 CFS of water rights to the City of Tetonia,” and, “We are also ready to address the need for a new well and will assist with that cost” (annexation narrative, p. 10). The city engineer notes that “The applicant proposes transferring water rights to the City as needed” (engineer’s review, p. 3).
What it doesn’t
- None of the applicant’s filings on this site, including the sewer reports, the two draft agreements, the engineer responses and the Nov. 19 response worksheet, states a dollar amount or a share for the third aerator or the additional lagoon cell.
- The draft development agreement does not mention Ordinance 2026-09, water mitigation, the aerator or the lagoon cell.
- The engineer’s “detailed review” of the draft development agreement “will follow separately” (engineer’s review, p. 1); it is not among the records on this site.
Question 4 of 7What happens to the 2025 rezone if no subdivision is approved?
What the record says
- The City Council approved the R-3 rezone of the 38 first-phase acres and a conditional use permit on Oct. 14, 2025, and adopted Ordinance 2025-06 on Dec. 9, 2025 (council minutes, Oct. 14, 2025, pp. 5-6; council minutes, Dec. 9, 2025, p. 2).
- The notice of decision conditions the rezone on a subdivision application “submitted within 18 months from the date of this approval (4/14/2027) and pursued in good faith,” and says: “If the subdivision is not applied for, denied, or the application and/or approval expires, the zone shall revert back to Transitional Agriculture (TA).” For the permit: “If the subdivision is not applied for on this site or the subdivision application review and/or approvals expire, then the CUP shall be null and void” (notice of decision, p. 4).
- The clerk’s copy of Ordinance 2025-06 gives the date as “(5/14/2027)” and says the zoning “shall revert back to Transitional Agriculture (TA) without further action by the City” (Ordinance 2025-06, as provided by the City of Tetonia clerk, Nov. 19, 2026, second of two unnumbered pages; quoted on the approvals page).
- The preliminary plat application is stamped received 10/9/26 (application, p. 1), and staff wrote that the revised package was “considered complete on 10/13/2026” (staff report, p. 2).
- Under the city code, “The developer shall submit the final plat within one (1) year of preliminary plat approval; otherwise, approval of the preliminary plat and development agreement shall become null and void” (city code 9-11-04-2(G)(3), p. 13).
What it doesn’t
- Neither the notice of decision nor the clerk’s copy of Ordinance 2025-06 says what pursuing the application “in good faith” requires, or who decides whether it has been.
- The two give different dates, April 14 and May 14, 2027, and neither says which one governs.
Question 5 of 7What would bind the applicant to its stated commitments?
What the record says
- The draft development agreement “shall become valid and binding only upon its approval by the City Council and its recording with the City Clerk and Teton County Recorder’s Office”; its signature lines are blank (draft development agreement, § 43 and signature pages). The draft annexation agreement’s effective date and signature pages are blank, and it says the “specific terms, timing, and allocation of responsibility” for improvements and water conveyances “are to be addressed in one or more separate development and other agreements and related approvals” (draft annexation agreement, Recital J and signature pages).
- Staff wrote on Oct. 28: “The Development Agreement is pending further review. More details in regards to the required improvements and Improvement Plans are needed before a D.A. can be finalized” (staff report, p. 4). Under the city code, after its hearing the commission sends “the development agreement draft” to the council with the plat (city code 9-11-04-2(F)(2)-(4), p. 12).
- Ordinance 2026-09 requires all required water mitigation to be completed before a final plat is recorded, a building permit issues or a conditional use permit gets final approval, or by a later date approved in a council-authorized development agreement, and leaves the council “final authority” over the quantity and form of mitigation (Ordinance No. 2026-09, as provided by the City of Tetonia clerk, Nov. 19, 2026, §§ 7, 9, pp. 4-5; approvals page).
- Idaho Code 67-6511A provides that a developer’s written commitments made as a condition of rezoning “shall be recorded in the office of the county recorder” and may be modified “only by the permission of the governing board after complying with the notice and hearing provisions” (quoted on the approvals page).
What the applicant’s filings say
- The comprehensive plan amendment narrative says the applicant “welcomes conditions the City determines are necessary to secure the public benefits described in this narrative” (narrative, p. 7).
- The annexation narrative says of the resort: “no field lighting will be installed, so no night games or associated noise or light will occur” (annexation narrative, p. 11).
What it doesn’t
- The text of neither draft agreement mentions the baseball resort, field lighting, a hotel or Ordinance 2026-09; the annexation agreement’s phasing map (Exhibit F) shows ball fields without naming them.
- Neither draft states a quantity of water rights to be conveyed; both tie reserved capacity to whatever water rights and infrastructure are contributed (draft development agreement, § 8; draft annexation agreement, § 5.4; see how the filings compare).
- No list of conditions of approval for the plat is among the records on this site.
Question 6 of 7How long is the comment window, and how much is in the record?
What the record says
- The hearing notice is marked posted Nov. 18, 2026. Written comments are due by 5 p.m. Monday, Nov. 30, 12 days later (Nov. 30 minus Nov. 18), and “Verbal and written comments will also be accepted during the public hearing” on Dec. 7 (hearing notice, p. 1). Thanksgiving, Nov. 26, falls in the window.
- The notice says: “Information pertinent to this application is available for public review upon request at Tetonia City Hall or by emailing clerk@cityoftetonia.com” (hearing notice, p. 1). Staff’s Oct. 28 report says “All application materials are available for download with this link” (staff report, p. 8).
- Staff wrote that “all application materials, revisions to the Plat and Development Agreement would need to be complete and ready for public comment by 11/20, which is the 15 day minimum” before the Dec. 7 hearing (staff report, p. 2). The city code calls for one notice in the official newspaper at least 15 days before the meeting (city code 9-11-04-2(F)(1)(b), pp. 11-12).
- Two city reviews are dated in the week before the notice: the city engineer’s, Nov. 12 (engineer’s review), and the planner’s, Nov. 16, with 60 numbered comments (planner’s memo; documents page).
- The four KLOA traffic studies in the application run 674 pages: 321 for the master plan study, 165 for the resort study, 105 for the Sept. 11 Phase I study and 83 for the May 21 Phase I study (master plan study; resort study; Phase I study; May 21 study; page counts are ours, from the posted files). This site’s Documents page posts 129 records; its 127 PDF files total 1,504 pages by our count.
- The Dec. 7 hearing is not the last step. On the plat, the City Council may “sustain, modify or reject the recommendations of the planning and zoning commission” (city code 9-11-04-2(G)(1), p. 12), and the city's contract planner wrote that for the larger proposal “the recommendation will go to City Council for another public hearing and decision” (planner’s memo, Sept. 15, 2026, p. 1).
What it doesn’t
- The notice does not list the documents that make up the application file or say how many pages it runs.
- The plat and the draft development agreement on this site are the versions received Oct. 9, 2026; no later revision of either is among the records here.
Question 7 of 7Who pays, and who gets paid back?
What the record says
- Teton School District #401 asks that the subdivision’s 90 single-family homes and 60 multifamily dwellings “voluntarily contribute $164,340 to the School Growth Contribution Fund,” based on $1,274 per single-family home and $828 per multifamily dwelling (school district letter, Sept. 1, 2026, p. 1). Its revised letter of Nov. 11 repeats the request and asks that land be dedicated to “a potential future school site,” suggesting five acres (school district letter, Nov. 11, 2026, p. 1, p. 2). The city’s contract planner wrote on Nov. 16 that the district “requested a per-lot contribution, which the Developer has agreed to provide through the Development Agreement” (planner’s memo, Nov. 16, 2026, p. 7).
- On Highway 33, the Idaho Transportation Department wrote that the development’s first draft traffic study “indicated signals were warranted at the access points with SH-33. These improvements along with turn lanes will be the responsibility of the developer” (ITD email, Aug. 24, 2026, p. 1). On the city’s own sewer system, the city engineer asks the applicant to “identify the developer’s proposed share of City sewer improvements” (engineer’s review, Nov. 12, 2026, p. 2; see question 3).
- The city’s fee resolution effective Oct. 1, 2026, sets a water hookup fee of $10,132 for a 3/4-inch or 1-inch line (Resolution 2026-04, p. 2) and a sewer connection fee of $8,463 per equivalent dwelling unit, with a single dwelling counted as one unit (Resolution 2026-04, pp. 2-3). That is $18,595 for a dwelling on its own line (DERIVED: $10,132 + $8,463 = $18,595).
- The first phase has 90 single-family lots and 60 townhouses (staff report, p. 1). If the drafts’ 75 percent credit (next section) applied to the 147 lots that are not “Affordable Lots,” at these rates, the developer would be credited about $2.05 million and the city would collect about $683,000 (DERIVED: 90 + 60 − 3 = 147; 147 × $18,595 = $2,733,465; × 0.75 = $2,050,099; × 0.25 = $683,366). The figure is ours and illustrative: it assumes one line and one sewer unit per dwelling, while the resolution notes that the water fee is halved for a second dwelling sharing a service line if installed at the same time (p. 2); rates can change; and the credit stops once it reaches the developer’s recoverable costs, which no document on this site states. The three Affordable Lots would owe no water or sewer fees (see the affordability page).
What the applicant’s filings say
- The draft development agreement says: “Developer shall construct all Improvements at its sole cost and expense” (draft development agreement, § 2). The annexation narrative says “The developer will be required to construct all new streets within the annexed land” and “all new sewer and water lines within the annexed land” (annexation narrative, p. 11), and, on water, “We are also ready to address the need for a new well and will assist with that cost” (p. 10).
- On the school district’s request, the annexation narrative says: “This is a voluntary contribution that Pinnacle Peak will happily commit to” (annexation narrative, p. 7).
- Both draft agreements would have the city “grant a credit ... equal to seventy-five percent (75%) of each water and sewer connection, tap, hook-up, capacity, buy-in, and/or impact fee” due for each dwelling unit, until the amount recovered reaches the developer’s “Recoverable Infrastructure Costs.” Those are defined as “all costs and expenses of every kind and nature incurred by the Developer, or by its affiliates” on water and sewer improvements that benefit the city’s systems, including wells, tanks and lift stations, “the cost of acquiring real property and interests in real property (including fee title, easements, rights-of-way, leases, and water rights),” and “engineering, surveying, legal, financing, carrying, and other soft costs” (draft development agreement, § 4.2(a)-(b); draft annexation agreement, §§ 5.5.1-5.5.2). The development agreement says the credit is “in addition to, and not in lieu of,” the Affordable Lots’ fee treatment (§ 4.2(b)).
- The draft annexation agreement adds two payments from later users outside the project. Where the city asks for a line sized or extended to serve land beyond the property, then for 30 years after the city accepts it, anyone outside the property who connects to it must first pay “a reimbursement equal to fifty percent (50%) of the Owners’ actual and verified cost” of that line (§ 5.2). “In addition,” anyone outside the property connecting to the owner-funded lines would pay a connection fee of “Five Hundred Thousand Dollars ($500,000.00) per connection,” “subject to periodic review and adjustment by the City so that the Connection Fee at all times represents a reasonable buy-in” (§ 5.3). The city would collect both and remit them to the owners, and for each the draft says the city’s obligation “shall not require the City to expend its own funds” (draft annexation agreement, §§ 5.2-5.3).
- If the law limits the credit, both drafts would have the city make up the difference; the development agreement’s version reads: “the City shall provide the Developer the economic equivalent of the unapplied portion through reimbursement from connection, capacity, or impact fees paid by future development, interproject transfers of credits, or any other lawful mechanism available under Idaho Code (including, without limitation, Idaho Code sections 67-8209, 67-8214, and 50-3102)”; they add that nothing in the section requires the city “to charge any fee below the actual cost of the service rendered” (draft development agreement, § 4.2(d); draft annexation agreement, § 5.5.4). Section 50-3102 is the definitions section of Idaho’s Community Infrastructure District Act (Idaho Code 50-3102).
- The drafts cap the total: the developer’s recovery “shall not exceed the total Recoverable Infrastructure Costs,” the intent being that it “be made whole for, but not recover more than,” those costs; the annexation draft counts the later users’ payments under §§ 5.2 and 5.3 toward that cap (draft development agreement, § 4.2(e); draft annexation agreement, § 5.5.5). The annexation draft says the cost-recovery arrangements “are entered into voluntarily and for good and valuable consideration and do not constitute development impact fees imposed under the Idaho Development Impact Fees Act” (§§ 5.1, 5.5).
- The economic impact report TischlerBise prepared for the Powell Family Group projects $6,286,000 in water and sewer hookup fees over the 20-year buildout of the full plan and says, “The developer pays these fees to the City for connection into the water and sewer system for each structure” (TischlerBise impact report, Dec. 23, 2025, p. 20). It states: “The analysis looks solely at revenues and does not project revenues based on expenditures” (p. 15).
What it doesn’t
- Neither draft agreement states the amount of the Recoverable Infrastructure Costs, so neither says how large the credit would be or how long it would run. Both leave the amount to a later written agreement between the city and the developer (draft development agreement, § 4.2(c); draft annexation agreement, § 5.5.3).
- The draft development agreement lists its improvement cost and bond schedules for Subphases 1 to 3 as Exhibits F, G and H; the copy on this site lists them but does not include them (draft development agreement, exhibit list). None of the applicant’s narratives, its Eagle Rock Engineering reports and responses, or the two draft agreements states what the improvements would cost.
- None of the applicant’s filings on this site, including the application forms, the narratives, the two draft agreements, the engineering reports and the TischlerBise report, names a lender, investor or other source of financing for the improvements.
- The text of neither draft agreement mentions the school district’s contribution, the requested school site, or the signals and turn lanes ITD says are the developer’s responsibility. The TischlerBise report does not mention a hookup fee credit.
- No record on this site proposes forming a community infrastructure district; the drafts’ citation of section 50-3102 is the only reference to that act we found in the record.
Have your say
Written comments to the Planning and Zoning Commission are due by 5 p.m. Monday, Nov. 30, 2026, and the commission takes spoken and written comments at its hearing at 7 p.m. Monday, Dec. 7 (hearing notice).